MANUFACTURED IN THE USA   /   SHIPPING NATIONWIDESALES & PROJECT SUPPORT   (951) 403-5738
Three gray switchgear cabinets with open doors and breaker panels on wooden pallets indoors.
AMERICAN BUILT   /   CALIFORNIA SERVED

Automatic Transfer Switches for Wastewater Facilities

Coordinate normal and standby power transfer with wastewater process priorities, pump controls and the conditions where equipment operates.

NEW SWITCHGEAR / AMERICAN COMPONENTS / BUILT TO SPEC01 — CALIFORNIA + NATIONWIDE
01
Made in the USAAmerican manufacturing
02
UL 891 switchboardsLow-voltage assemblies, as applicable
03
Short lead timesSchedule confirmed with quote
04
Nationwide shippingServing California & beyond
BUILT AROUND YOUR PROJECT / 01

Map the Process Before Selecting Transfer Equipment

A wastewater facility’s transfer scheme should start with process consequences, not simply a list of electrical loads. Identify which pumps, controls, ventilation systems, instrumentation and communications must remain available during loss of normal power, and which can wait or remain disconnected. A lift station with limited wet-well storage may require a different restoration priority from a treatment plant with multiple process stages and onsite storage. Document normal and standby sources, distribution points, control power and any loads served through separate transfer equipment. Then trace how loss of a source affects each process and what operators need to monitor during recovery. This functional picture helps the design team determine transfer locations, load groups and operating modes without assuming one arrangement fits every site. Qualified electrical and controls professionals should review the sequence against process requirements, applicable codes and the facility’s emergency-power plan.

Define Transfer and Pump Restart Sequences

When normal power fails, an automatic transfer switch (ATS) detects the source condition and initiates transfer according to its control logic and project settings. The standby source may need time to start and stabilize before the ATS permits connection; acceptable voltage, frequency, phase and time delays are design inputs to confirm. Once standby power is available, pump loads should not necessarily restart all at once. Simultaneous motor starting can impose a substantial demand on a generator and may cause voltage or frequency disturbance. A staged sequence can prioritize critical pumping, allow equipment to settle, then restore additional pumps and support loads. Confirm how variable-frequency drives, soft starters, PLCs and local control stations behave through an outage and transfer. Specify whether automatic restart is permitted, whether an operator must acknowledge alarms, and how failed starts or a second source failure are handled. Validate the sequence with controls and generator specialists.

THE DETAILS THAT DRIVE THE BUILD
Project specifications to define with your quote
SystemVoltage, phase, current and available fault current
ConfigurationLineup, protection, controls and enclosure as specified
ComplianceApplicable standards and listing confirmed for the assembly
DeliveryCalifornia and nationwide; schedule confirmed by quote

Match Standby Capacity to Operating Conditions

Standby power requirements depend on more than the connected-load total. Establish which pumps may operate together, expected motor-starting characteristics, drive behavior, auxiliary loads and the minimum process capacity needed during an outage. Consider whether the facility must support peak inflow, a reduced operating mode, or only essential pumping and controls. Generator capability, fuel arrangements, transfer settings and the number of available source paths all affect what can be restored and when. A load-priority schedule can make constraints explicit, but it must align with hydraulic and process limits; shedding a load that appears nonessential electrically could impair safe operation or cause an overflow risk. Identify any loads that require uninterrupted power rather than a transfer interval, since an ATS does not itself provide a no-break supply. Have qualified professionals coordinate source capacity, protection, motor-starting limits and applicable code requirements for the specific installation.

Account for Wet and Corrosive Environments

Wastewater sites may expose electrical equipment to humidity, condensation, washdown, corrosive gases, chemical vapors or airborne contaminants. Conditions vary between a conditioned control room, a pump station cabinet and equipment near a wet well, so describe the actual installation rather than relying on a broad label such as “outdoor.” Provide the mounting location, enclosure setting, ambient temperature range, ventilation or heating provisions, and any known exposure to corrosive agents or water. These details inform enclosure selection, materials, coatings, sealing, drainage and maintenance access, subject to engineering review and the equipment’s applicable requirements. Also consider how technicians can inspect controls and terminate conductors without compromising environmental protection. Corrosion and moisture can affect connections, mechanisms and sensing circuits over time; a practical inspection and maintenance plan is therefore part of reliability planning, not an afterthought. Confirm that the specified arrangement suits the site conditions and local requirements.

Prepare a Useful Project Package

For a project review, provide one-line diagrams, source and load schedules, available fault-current information, generator data, motor and drive details, control schematics, and the intended normal-to-standby operating narrative. Note pump priorities, restart delays, interlocks, alarm points, bypass or isolation expectations, and any manual operating steps. Identify environmental conditions, installation space, conductor entry preferences and interfaces with existing PLC or supervisory systems. For replacement or expansion work, document the existing equipment and constraints while keeping any modernization scope focused on the customer’s own installation. The design team can then clarify transfer ratings, configuration, protection coordination, sensing logic and applicable standards for the specific equipment; requirements should be verified rather than assumed from a general product description. Switchgear Builder California builds new equipment in the USA with American components and supplies customers in California and nationwide. Schedule-sensitive options may be discussed after project review, without assuming a particular delivery date.

READY WHEN THE PROJECT IS

Let's get power moving.

From the first specification to the final shipment, start with a conversation about your project.

REQUEST A QUOTE